It takes 12 men 5 days to complete a job. Work out how many days it would take 3 men to complete the same job.

Respuesta :

Esther
Esther Esther
  • 03-03-2022

Answer:

20 days

Step-by-step explanation:

It takes 12 men 5 days to complete a job. Work out how many days it would take 3 men to complete the same job.

12 * 5 = 60

60/3 = 20

It will take 3 men 20 days to do the same job

Answer Link

Otras preguntas

Please help: Investing $2,000,000 in TQM's Channel Support Systems initiative will at a minimum increase demand for your products 1.7% in this and in all futur
What is a tetrad? A. A chromatid before meiosis B. Another term for a sperm cell C. A haploid cell produced by meiosis D. Two sets of sister chromat
The table shows masses of different types of nuts that Nathan buys. He plans to mix the nuts and then separate them into bags. Each bag will have 1.2 kg of nuts
Approximately what per cent does Central America contribute to the total amount of carbon dioxide produced in the world
Subtract. (9j+9)–(8j+4)
what do you use to record your computer
The beautiful girl is smiling compound coordinate attribute
The force of attraction between earth and objects on its surface is
If an area has all the wolves that it can support, the wolf population has reached its ______?
How to figure out 2.73+0.003+0.158